Cedar Lane Paving Project - MILLING/PAVING Begins November 19!
*IMPORTANT NOTIFICATION*
*Cedar Lane Paving Project MILLING/PAVING begins November 19!*
Please be advised that the County is scheduled to mill/pave Cedar Lane from Teaneck Road to the Hackensack border beginning Tuesday, November 19th.
Milling will begin at the Hackensack Border on NOV. 19th.
Paving tentatively scheduled for Nov. 25th.
NO ROAD WORK WILL BE SCHEDULED FOR NOV. 27th.
**DATES SUBJECT TO CHANGE**
Expect detours and traffic delays during the milling and paving process. Please plan an alternate route if possible.
Notifications will continue to be posted.
Emergency NO PARKING signage will be in the area where needed.
Thank you for your continued patience & cooperation during this paving project.